Friday

Power interruptions on 13 September 2024

KPLC listed 8 areas in Mt. Kenya, Nairobi, South Nyanza and Western for planned maintenance on this day. Power is off during the hours shown for each area.

Mt. Kenya region 2 areas

Mukangu, Gatina

8.00 A.M. – 5.00 P.M.

Kirigu C/Fact, Gatina C/Fact, Gakuyu Sec Sch, Gatina Village, Mukangu Dispensary, Mukangu Mkt, Mukangu C/Fact, Safaricom & Airtel Boosters, Mukangu Sec Sch

Mukangu, Gatina

8.00 A.M. – 5.00 P.M.

Kirigu C/Fact, Gatina C/Fact, Gakuyu Sec Sch, Gatina Village, Mukangu Dispensary, Mukangu Mkt, Mukangu C/Fact, Safaricom & Airtel Boosters, Mukangu Sec Sch

Nairobi region 2 areas

South Nyanza region 2 areas

Western region 2 areas

About this day

These areas come from KPLC's planned interruption notice. KPLC schedules this work in advance to maintain and upgrade the network. The notice on kplc.co.ke is the official source. If the hours change, KPLC announces it there.